**Job schedules** in WorkBook are created and accessed via the **jobs** module > **select job** from list > **tasks** tab. This is where you plan the tasks, timeline and resources required to deliver the job. Within a job schedule you can create a series of phases and tasks, allocate people or roles, book hours to them and assess real-time resource capacity as you build out the timeline.

| **ON THIS PAGE YOU’LL FIND:** |
| --- |
| > Macro (toc) |

---

## SCHEDULE STRUCTURE

The schedule breakdown structure within WorkBook is fixed. A schedule must contain at least one phase. 

![image](media://f95da17c-4f3c-4c76-a5e3-0fb124a0add1)

|  |  |
| --- | --- |
| **LEVEL** | **DEFINITION** |
| **Schedule** | The timeline or task plan belonging to a job |
| **Phase** | A phase is a parent used to group multiple tasks |
| **Task** | A piece of work that has:<br>1. A start date/end date
2. A duration
3. Assigned resource/s with a number of hours and allocation date/s |

---

## NAVIGATION: SETTINGS TAB

Schedules are accessed via the **tasks** tab on a job.  

![image](media://82ab2308-c1fd-439d-92dc-426e2431c073)

| **NUMBER** | **FUNCTIONALITY** |
| --- | --- |
| **1** | **Create a new schedule** button allows you to create a new schedule against the current job. *Note: You can have multiple schedules on a single job* |
| **2** | The **duplicate schedule** button allows you to copy the existing schedule to easily create variations |
| **3** | The **delete schedule** button allows you to delete the current schedule<br>*Note: This can only be done when the schedule is inactive* |
| **4** | The **save as a template** button allows you to save your current schedule as a template which can later be copied into other jobs to save time |
| **5** | The **update task data** button allows you to refresh the schedule data by:<br>- recalculating resource capacity booking, or
- updating prices to match the current job price list (rate card) |
| **6** | The **copy data from** button, allows you to copy data into you schedule from:<br>- a price quote
- a schedule from another job
- or a template |
| **7** | The **reorder tasks** button allows you to reorder tasks based on:<br>- the order of creation
- start date
- end date |
| **8** | The **reschedule tasks** button allows you to select the phases and/or tasks you wish to reschedule by:<br>- the number of calendar days
- the number of working days
- new start date
- new deadline |
| **9** | Makes your schedule **active **or **inactive** |
| **10** | **Distribute hours by** allows you to distribute task hours in one of two ways:<br>1. Use first available capacity (this is WorkBook’s default)
2. Even distribution of hours |
| **11** | The **resource booking level** looks at the different capacity levels of resources. The most common used are:<br>- Basic Time: standard employee hours e.g. 7.6 hour per day
- Ideal Time: this is time set in an employee’s capacity profile and could be less than, the same as or more than basic time |

---

## NAVIGATION: PHASES TAB

![image](media://8d89171c-67a5-4411-8961-4df6deadf8b5)

| **NUMBER** | **FUNCTIONALITY** |
| --- | --- |
| **1** | **Create a new phase** button for adding new phases |
| **2** | **Insert default phases** button will insert any default phases that have previously been setup |
| **3** | **Merge selected phase with another phase** button allows you to merge phases together |
| **4** | The **create a task for all phases where there is not already an assigned task** button will create a task for each phase that is currently missing tasks |
| **5** | **Remove the selected phase** button will delete the phase you have highlighted. *Note: You cannot delete a phase that contains tasks, first move or delete the tasks and then delete the phase. * |
| **6** | The **delete unused phases** button will delete all phases that do not have a task assigned to the phase |
| **7** | These buttons will reorder phases by allowing you to:<br>- move a phase down
- move a phase up
- re-sort phase numbering |

---

## NAVIGATION: TASKS TAB

![image](media://933d1c0b-f537-4fbf-88be-650a3794650f)

|  |  |
| --- | --- |
| **NUMBER** | **FUNCTIONALITY** |
| **1** | Add new tasks to your schedule by typing the task name into the **new task field > **hit **enter** to add, repeat to add each new task |
| **2** | These buttons allow you to:<br>- Update task data
- **Copy schedule data** (used to copy schedule templates into jobs)
- Reorder tasks
- Reschedule tasks |
| **3** | **Task actions buttons**<br>- Duplicate task
- Delete task
- Set task as done |
| **4** | See the total **value** of scheduled work:<br>- To turn on go to **filter** > tick the **show schedule total price **checkbox (this allows you to see the total sales value of the schedule as you assign resources and book hours) |
| **5** | Available schedule views are:<br>- Gantt chart
- Grid view
- Timeline
- List view |
| **6** | **Filter** the schedule using the following criteria:<br>- Canvas Period: day, work week, month, quarter etc
- Filter Options: hide completed tasks, hide future tasks etc.
- Toolbar Options: show the schedule price and job progress |
| **7** | The **booked resources **button opens a panel at the bottom of the screen for easy task resourcing and marking tasks as done |
| **8** | The **task settings **button opens the task card, where you can view and amend task settings, including task colours, milestones, status and whether time entry is allowed |
| **9** | The **booked resources sub-grid** allows you to book people or roles and enter the number of hours on a specific task (selected in the main grid) |
| **10** | The **task capacity booking options** allows you to override working hours and book individuals/roles on weekends or above the usual hours per day |
| **Shortcut keys** | Select the task you want to edit:<br>- Click T on your keyboard to edit the task name
- D to edit the dates
- W to edit the duration |

---